Auditing Performance Issues
Impact of Auditing on Other Facilities
Enabling auditing on a project increases the time taken for most actions. For most modeling tasks, this increase is insignificant; however, there are some situations where the difference is more substantial.
Large Deletions
Deleting large packages or package structures, or large numbers of elements, takes significantly longer with auditing on. You might disable auditing before performing such a deletion.
XMI Imports
Importing XMI takes longer with auditing enabled. A project-level option is provided for disabling auditing of XMI Imports.
Reverse Engineering
Reverse engineering code takes longer with auditing enabled. A project-level option is provided for disabling auditing of reverse engineering.