Set Cost Parameters on Resource
Create the BPMN Model (Resources)
- In the Browser window create a StartEvent1, a GlobalTask1, two abstractTasks called Task (by Junior) and Task (by Senior), and an EndEvent1.
- the elements from the Browser window onto a diagram, pasting GlobalTask1 as an Invocation (Call Activity) named call global (by Junior).
- Connect the elements with Sequence Flows.
- Create two BPMN2.0 Resource elements: Junior Developer and Senior Developer.
BPSim Configuration
Create a Business Process Simulation configuration Artifact in the diagram, right-click on it and select the 'Configure BPSim' option, then set the configuration to link to the Package containing the BPMN model elements and configure these BPSim parameters as indicated.
Parameter |
Setting |
---|---|
Scenario Parameters |
This Time Unit is used to calculate the Time Cost (Time cost = Unit Cost * Time), so make sure the Unit Cost is based on the correct Time Unit. |
Control Parameters |
|
Time Parameters |
|
Resource Parameters |
|
Cost Parameters |
|
Simulation
- On the 'Configure BPSim' dialog, click on the 'Execute' tab.
- Click on the button'.
- When the simulation is complete, click on the 'Review' tab, and on the 'Standard Results Report' tab.
- the report by clicking on the button and selecting the 'Show only Non-Empty Items' option.
Analysis
Resource |
Results |
---|---|
Junior Developer |
|
Senior Developer |
|